The Saïss Water Conservation Project

  • Adaptation
  • Under implementation
Date approved
06 Apr 2017
Est. completion
31 Jan 2027
ESS Category
Category B
Financing
Public sector
Entity
European Bank for Reconstruction and Development

Overview

Improving the climate resilience of agricultural systems in the Saïss Plain.

The resilience of the Saïss Plain is threatened by declining and unpredictable rainfall due to climate change, coupled with unsustainable groundwater use. Water scarcity is chronic, and demand is projected to increase in Morocco. 80% of abstracted water is used for agricultural purposes, so this water scarcity threatens agricultural production and rural livelihoods, with climate change being an important risk amplifier.

This project will switch the Saïss Plain from the use of highly unsustainable groundwater to sustainable surface water. A bulk water transfer scheme from the M’Dez dam to the Saïss Plain will be created, along with the preparation of a Public-Private Partnership (PPP) to implement new irrigation networks. This critical infrastructure will facilitate the transfer of water from a river basin with a surplus of water to the Sebou-Saïss basin with a shortfall of water resources.

Community involvement in water governance will be promoted, together with improved awareness of climate resilience issues among end users of water services, and the promotion of best-practices, efficient irrigation techniques with a significant demonstration impact across sector and region.

The result will be increased efficiency of water use and services, promoting drip irrigation and modern water demand management methods, thus strengthening capacity for adaptation to climate change in the Sebou-Saïss basin.

The project has an estimated lifespan of 40 years.

Result areas

Countries

Regions

Priority groups

Project timeline

  • Pipeline

    379 days

    • Concept note received

    • Funding proposal received

    • Cleared by GCF Secretariat

  • Approved

    301 days

    • Approved by GCF Board

    • Cleared by iTAP

    • Legal opinion on AE's Internal Approval

    • FAA executed

  • Under implementation

    3,058 days so far

    • FAA effective

  • To be completed

    230 days to go

    Not started

  • Total project value $ 241 million

  • Total number of beneficiaries 2.2 million