FP018

Scaling-up of Glacial Lake Outburst Flood (GLOF) risk reduction in Northern Pakistan

Scaling-up of Glacial Lake Outburst Flood (GLOF) risk reduction in Northern Pakistan

  • Status Under implementation
  • Date approved 14 Oct 2016 at B.14
  • Est. completion 12 Jul 2022
  • ESS Category Category B

Rising temperatures have melted glaciers, creating glacial lakes in Northern Pakistan. These carry the risk of outburst flooding events, threatening over 7 million people. Early warning systems, engineering structures and disaster management policies will reduce risk, protecting local communities and providing early warning of devastating flood events.

The melting of the Hindu Kush, Karakoram, and Himalayan glaciers in Northern Pakistan due to rising temperatures have created 3,044 glacial lakes in the federally-administered territory of Gilgit-Baltistan (GB) and the province of Khyber Pakhtunkhwa (KP). It is estimated that 33 of these glacial lakes are hazardous and likely to result in glacial lake outburst floods. Such flooding releases millions of cubic metres of water and debris in just a few hours, resulting in the loss of lives, destruction of property and infrastructure, and severe damage to livelihoods in some of the most remote areas of Pakistan.

The project will build 250 engineering structures including damns, ponds, spill ways, tree plantation and drainage to reduce risk. At the same time, the development of disaster management policies and the introduction of weather monitoring stations, flood gauges, hydrological modelling and early warning systems will increase the ability to respond rapidly to flood scenarios.

The project has an estimated lifespan of 15 years.

Total project value

 

Beneficiaries

 

Direct
696,342
Indirect
28,536,658
Theme

Adaptation

Result areas

Project timeline

Pipeline

30 May 2015 - 504 days

Concept note received

30 May 2015

Funding proposal received

31 Jul 2015

Legal opinion on AE's Internal Approval

28 Sep 2016

Approved

14 Oct 2016 - 272 days

Approved by GCF Board

14 Oct 2016

Cleared by iTAP

14 Oct 2016

FAA executed

19 May 2017

Under implementation

12 Jul 2017 - 1,171 days so far

FAA effective

12 Jul 2017

Disbursement - USD 10,504,366

21 Mar 2018

Annual Performance Report

23 Mar 2018

Annual Performance Report

01 Mar 2019

Completed

12 Jul 2022 - 656 days to go

One region

  • Asia-Pacific

One country

USD  
  • Financing
    • Private sector
    • Public sector
  • Size
    • Micro
    • Small
    • Medium
    • Large

GCF financing28% disbursed

InstrumentAmount
GrantUSD 36,960,000

Cofinancing

CofinancerInstrumentAmount
Co-FinancingGrantUSD 500,000

GCF Contacts

General media inquiries

GCF Communications
Phone +82 10 4458 7751
Send e-mail

Request for information

GCF Information Disclosure
Request information about this project

Project complaints and grievances

GCF Independent Redress Mechanism (IRM)
Phone +82 32 458 6157
File a complaint

Integrity issues

GCF Independent Integrity Unity (IIU)
Phone +82 32 458 6155
Send e-mail

Accredited Entity

United Nations Development Programme

Mr. Pradeep Kurukulasuriya
Executive Coordinator and Director, Global Environment Finance
304 East 45th Street, FF-9th Floor, New York, NY, United States
Phone +1 (212) 906-5884
pradeep.kurukulasuriya@undp.org
Mr. Robin Merlier
Environmental Policy Specialist Global Environmental Finance, Bureau for Policy and Programme Support (BPPS)/Global Policy Network
Phone +1 2129065842
robin.merlier@undp.org

National Designated Authority

Pakistan

Ministry of Climate Change

Ms. Naheed Durrani
Federal Secretary, Ministry of Climate Change
3rd Floor, Ministry of Climate Change, LG&RD Complex, G-5/2, Islamabad, Pakistan
Phone +9251-9224579
pakistangcf@gmail.com
Mr. Ahsanullah Khan
Officer in Charge-Climate Finance Unit
3rd Floor, Ministry of Climate Change, LG & Rd Complex, G-5/2, Islamabad, Pakistan
Phone +9251-9245626
pakistangcf@gmail.com

News + Stories

The positives of preparing for disaster

12 Jun 2018 / A guide to GCF's support for climate change early warning systems