Tonga Coastal Resilience

  • Adaptation
  • Under implementation
Date approved
18 Jul 2024
Est. completion
27 Aug 2031
ESS Category
Category B
Financing
Public sector
Entity
United Nations Development Programme

Overview

Tonga is highly vulnerable to climate change impacts, including increases in temperature and precipitation, more intense tropical cyclones, and rising sea levels. Extreme events such as Tropical Cyclones Ian in 2014, Gita in 2018, and Harold in 2020, have caused devastating flooding, destruction of physical assets, and substantial economic losses, underscoring the need for immediate and comprehensive climate action. 

To overcome these challenges, this project will drive a transformational shift in coastal adaptation in Tonga, empowering local stakeholders and communities to build a resilient and sustainable future. It will achieve this by establishing a national multi-sectoral platform to integrate climate risk information into local development planning; strengthening local capacities to collect and manage data for coastal adaptation planning; and constructing over four kilometres of sea defences in vulnerable coastal areas. Additionally, the project will address issues such as land-use planning and voluntary retreat to enhance Tonga’s long-term resilience.

Result areas

Project timeline

  • Pipeline

    2,664 days

    • Funding proposal received

    • Legal opinion on AE's Internal Approval

    • Cleared by GCF Secretariat

    • Cleared by iTAP

  • Approved

    41 days

    • Approved by GCF Board

    • FAA executed

  • Under implementation

    658 days so far

    • FAA effective

  • To be completed

    1,899 days to go

    Not started

  • Total project value $ 23.9 million

  • Total number of beneficiaries 100 thousand

Financing

GCF-financing

0.0%

USD

Co-financing

0.0%

USD

USD 23.9 million

Show details

GCF-financing

29% disbursed

  • Grant USD 22,656,409
  • Total GCF-financing USD 22,656,409

Co-financing

  • Grant USD 1,200,000
  • Grant USD 63,000
  • Total co-financing USD 1,263,000