Overview
Supporting the construction of 8-11 renewable energy projects in Kazakhstan, with a total capacity of 330 MW.
Around 91% of Kazakhstan’s electricity is generated from fossil fuels, making it one of the largest emitters of greenhouse gases in Central Asia. Diversification of energy sources, and the decarbonisation of the economy is a priority of the Kazakhstan government, which is introducing feed-in tariffs and an auction scheme to promote this transition. However, lack of appropriate financing mechanisms has delayed the development of new projects to respond to these policies. GCF’s investment will scale-up investment in renewables, crowding-in low-carbon investors through a programme of investment, and creating a viable alternative to cheap coal-based power. The programme will also provide technical assistance, building institutional capacity for energy integration, policies and planning.
The project has an estimated lifespan of 20 years.
Result areas
Countries
Project timeline
-
Pipeline
285 days
-
Concept note received
-
Funding proposal received
-
Cleared by iTAP
-
-
Approved
219 days
-
Approved by GCF Board
-
Legal opinion on AE's Internal Approval
-
FAA executed
-
-
Under implementation
2,961 days so far
-
FAA effective
-
-
To be completed
327 days to go
Not started
Other Data
- Size
- Large
- Project number
- FP047
- Risk category
- Category A
- Subtype
- Private sector
- Theme
- Mitigation
- Status
- Under implementation
- Duration
- 5
-
Total project value $ 557 million
-
Tonnes of CO2 equivalent avoided 12.9 million
Financing
GCF-financing
0.0%
USD
Co-financing
0.0%
USD
USD 557
million
Show details
GCF-financing
92% disbursed
- Loan USD 106,000,000
- Grant USD 4,000,000
- Total GCF-financing USD 110,000,000
Co-financing
- Loan USD 214,000,000
- Loan USD 46,500,000
- Equity USD 137,000,000
- Grant USD 3,000,000
- Loan USD 46,500,000
- Total co-financing USD 447,000,000
Documents
-
2024 Annual Performance Report for FP047: GCF-EBRD Kazakhstan Renewables Framework
- Annual Performance Report
- 01 Mar 2025
- EBRD
- FP047
-
Interim evaluation report for FP047: GCF-EBRD Kazakhstan Renewables Framework
- Evaluation report
- 11 Dec 2023
- EBRD
- FP047
-
Gender assessment for FP047: GCF-EBRD Kazakhstan Renewables Framework
- Gender assessment
- 31 Jan 2018
- EBRD
- FP047
-
Gender action plan for FP047: GCF-EBRD Kazakhstan Renewables Framework
- Gender action plan
- 31 Jan 2018
- EBRD
- FP047
-
GCF-EBRD Kazakhstan Renewables Framework
- Approved funding proposal
- 08 Nov 2017
- EBRD
- FP047
-
Environmental and social safeguards (ESS) report for FP047: GCF-EBRD Kazakhstan Renewables Framework
- Environmental and Social Safeguards report
- 12 Sep 2017
- EBRD
- FP047
Project contacts
Find the appropriate contacts for this project, including partner organizations and responsible entities.
See contact details
Project contacts
Entity info
-
Ms. Elodie Loppé
Secondary
Principal Manager, Donor Partnerships, Vice-Presidency Impact & Partnerships
GCF team
-
Press enquiries and interviews
-
GCF Communications
-
-
Request for information
-
GCF Information Disclosure
-
-
Project complaints and grievances
-
GCF Independent Redress Mechanism (IRM)
-
-
Integrity issues
-
GCF Independent Integrity Unity (IIU)
-
National Designated Authority
Ministry of Ecology and Natural Resources of the Republic of Kazakhstan (Kazakhstan)
-
Mr. Mansur Oshurbayev
Primary
Vice-Minister
Mangilik el ave, 8, House of Ministries, 14 entrance, office 433, Astana, Kazakhstan
-
Mrs. Saule Sabieva
Secondary
Director of Climate Policy Department
-
Mrs. Aizhan Mamedaliyeva
Operational Focal Point
Chief expert of Adaptation to Climate Change Unit, Climate Policy Department
-
Mrs. Shattyk Tastemirova
Operational Focal Point
Head of Adaptation to Climate Change Unit, Climate Policy Department